Announced Allocations
The Central Brisbane River Water Supply Scheme is running with the following announced allocations:
| AA High Priority A
Last updated 1 July 2012
|
100% |
| AA Medium Priority
Last updated 1 July 2012
|
100%
|
Parameters used in Calculating Announced Allocations
Formula for AA High Priority
- 100% when the combined percentage of useable volume in storage of Wivenhoe and Somerset dams is greater than or equal to 25%
- When the combined percentage of useable volume in storage of Wivenhoe and Somerset dams is less than 25% the AA High must be calculated using the following formula as set out in s78 of the Moreton Resource Operations Plan:
AAHPA = ((UV-(AAMPxMPA)+DIVHPA+DIVMP)/HPAA) x 100
Parameters for AA High Priority calculation
The following parameters were used in calculating the current AA High:
| UV (Useable Volume) | 1,146,811 ML |
| AAMP (Medium Priority Announced Allocations) | 100 % |
| MPA (Medium Priority Water Allocations) | 7,041 ML |
| DIVHPA (High Priority Diversion) | 0 |
| DIVMP (Medium Priority Diversions) | 0 |
| HPAA (High Priority A Water Allocations) | 279,000 ML |
Formula for AA Medium Priority
- As per column 2 of the following table corresponding to the combined percentage of useable volume in storage of Wivenhoe and Somerset dams in column 1.
| Combined Percentage of Useable Volume in Storage of Wivenhoe and Somerset Dams
(CPUVS)
|
Announced Allocation for Medium Priority Water Allocations (AAMP)
(% of nominal volume)
|
| 0%-14.9% | 0% |
| 15%-24.9% | 15% |
| 25%-29.9% | 25% |
| 30%-34.9% | 40% |
| 35%-39.9% | 55% |
| 40%-44.9% | 70% |
| 45%-49.9% | 85% |
| 50%-100% | 100% |
- The combined percentage of useable volume in storage of Wivenhoe and Somerset dams must be calculated using the following formula as set out in s77 of the Moreton Resource Operations Plan:
CPUVS = ((UVWivenhoe + UVSomerset)/CUFSV) x 100
Parameters for AA Medium Priority calculation
The following parameters were used in calculating the current AA High:
| UVWivenhoe (Useable Volume) | 838,998 ML |
| UVSomerset (Useable Volume) | 307,813 ML |
| CUFSV (Combined Useable Full Supply Volume) | 1,543,783 ML |
Please refer to the Moreton Resource Operations Plan for further details regarding Medium Priority Announced Allocations in the Central Brisbane River Water Supply Scheme.
Application form for seasonal water assignment approval (temporary transfer)
If you are in the Central Brisbane River scheme and wish to trade water, please complete the Central Brisbane River Temporary Transfer form and submit it to Seqwater.
If you have any further questions please contact Seqwater on 1800 077 005 or email irrigatorquestions@seqwater.com.au. Our postal address is: PO Box 16146, City East Queensland 4002.